RemScan Enabled Excavation Delineation for Hydrocarbon-Impacted Soil

A Monte Carlo Cost–Risk Comparison of Lab-Only vs RemScan Workflows Integrated with the GXLab Platform

Executive Summary

 

This report evaluates excavation delineation outcomes for hydrocarbon-impacted soil using a Monte Carlo simulation framework. It compares a conventional lab-only sampling workflow against a Rapid Scan (RemScan) workflow integrated with the GXLab platform.

Across thousands of simulated plumes, the analysis shows that increasing vertical measurement density using low-marginal-cost Rapid Scan data materially reduces under-excavation risk. This reduction in missed contamination events dominates total project cost when the consequences of rework, delay, and regulatory exposure are moderate to high.

Key findings from the simulations

  • Holding borehole locations constant but increasing vertical resolution reduced mean total remediation measurement cost by ~17–20 percent across low, medium, and high penalty scenarios.
  • Modestly increasing borehole density while maintaining high vertical resolution reduced mean measurement cost by ~48–60 percent.
  • In all scenarios, the RemScan workflow reduced the high-cost tail driven by under-excavation events, even when conservative assumptions were applied to measurement error.
  • Once a core exists, dense vertical data becomes economically rational because marginal analysis cost is low relative to excavation and rework risk.
  • Near-real-time integration with GXLab compounds value by shortening decision cycles and reducing stop-start excavation behaviour.

Table ES-1. Total cost per plume (simulation summary; currency in AUD million (1AUD approx. 1.4USD)

Case Penalty Lab mean RemScan mean Lab median RemScan median Mean reduction
1 Low 0.37 0.31 0.21 0.12 17.3%
1 Medium 1.07 0.86 0.60 0.32 19.0%
1 High 2.64 2.12 1.46 0.78 19.6%
2 Low 0.55 0.28 0.30 0.16 48.0%
2 Medium 1.59 0.68 0.87 0.19 57.0%
2 High 3.95 1.59 2.15 0.21 59.8%

Interpretation of the cost tiers: The simulations compute total cost as (over-excavation volume × $80/m³) + (under-excavation volume × penalty) + sampling/analysis costs. Under-excavation penalty is evaluated as Low=$200/m³, Medium=$600/m³, High=$1,500/m³. These tiers represent best-case through worst-case consequences when contamination is missed and rework is required.

GXLab platform integration value: The direct financial savings shown above do not fully capture the operational value of a fast feedback loop. With RemScan results uploaded into GXLab in near real time, excavation boundary updates and volume estimates can be produced immediately, enabling tighter decision cycles, fewer demobilisation/remobilisation events, and less idle time waiting on laboratory turnaround.

Download the free report below to find out more.